TPS inform the situation probelm of SSMC 2 about inspection.Q-Gate have problem inspection not on time because manpower current not enough refer calculation need use manpower 3 man/shif but current is have 1 man/shift effect F/G part not enough for delivery, over space for keep waiting part for inspection, other management. So I'd like to request QA concern to set manpower for fix this problem completely