The problem could be remedied by widening the channel but it has been noted that not only would the cost of dredging be very high, but continuous maintenance would be needed. Maintenance costs alone are estimated at about 300 million baht a year.
Moreover, as the port is located within Bangkok Metropolis, its boundaries are confined within strict limits, which means that the onshore area for cargo handling and storage is also limited. Although current throughout is only 3.2 million tons per annum of containerised cargo, congestion is already a major problem.
It has also been proposed that the existing port at Sattahip provide expansion facilities for Klong Toey. However, the ESB office pointed that smaller feeder ships carrying cargo transshipped from Singapore or Hong Kong were vessels that could only call at Sattahip, while future cargoes passing through major international ports were
likely to be containerised. Thailand, therefore, would not be able to accommodate direct transoceanic shipments from Europe, the Americas and the Middle East.
It was also noted that the costs of developing Sattahip Port would be very high, involving widening of the dredged channel from the existing 100 metres to 160 metres, deepening of the channel and basin from 10 metres to 13 metres and construction of new outboard berths.
The office noted that the cost, in relation to the increased capacity, made it more viable to develop a port at Laem Chabang, especially in view of the latter's potential for development. It was, therefore proposed that Lerm Chabang be made the site of the country's second commercial port.
It was also decided that an industrial port be set up at Mab Ta Phud in Rayong.
However, both projects were nearly pulled off the drawing board because of the country's heavy external debt burden.
When the external debt service ratio neared the critical level of 30% the Government decided that no more unnecessary and non-urgent foreign loans would be borrowed. The aim of this was to keep external debt borrowings in fiscal 1986 within the US$ 1,000 million ceiling, thus staving off a financial disaster for the country.
The Cabinet then decided to set up a three-man committee to review the ESB because it was noted several times that most of the projects required huge foreign borrowings, which could push the external debt service ratio beyond the critical mark.
They had 45 days to review the entire programme during which time it was reported that the two deep-sea port projects were the likely victims if the ESB was scaled down in size.
lt, therefore, came as a surprise when the Cabinet announced on ChristmaS Eve of 1985 that the entire programme would proceed as planned.
According to the ESB plan, construction of the Mab Ta Phud Port will begin in May 1986 and completed by October 1989. Investment in the initial stage would be around 5,820 million baht..
Meanwhile, construction of the Laem Chabang deep-sea port will begin in September 1986 and completed by July 1990. Investment in the first phase will total 6,860 million baht.
The idea to construct a new sea port at Laem Chabang also won support from the Bangkok Shipowners and Agents Association. (BSM)
The problem could be remedied by widening the channel but it has been noted that not only would the cost of dredging be very high, but continuous maintenance would be needed. Maintenance costs alone are estimated at about 300 million baht a year. Moreover, as the port is located within Bangkok Metropolis, its boundaries are confined within strict limits, which means that the onshore area for cargo handling and storage is also limited. Although current throughout is only 3.2 million tons per annum of containerised cargo, congestion is already a major problem. It has also been proposed that the existing port at Sattahip provide expansion facilities for Klong Toey. However, the ESB office pointed that smaller feeder ships carrying cargo transshipped from Singapore or Hong Kong were vessels that could only call at Sattahip, while future cargoes passing through major international ports werelikely to be containerised. Thailand, therefore, would not be able to accommodate direct transoceanic shipments from Europe, the Americas and the Middle East. It was also noted that the costs of developing Sattahip Port would be very high, involving widening of the dredged channel from the existing 100 metres to 160 metres, deepening of the channel and basin from 10 metres to 13 metres and construction of new outboard berths. The office noted that the cost, in relation to the increased capacity, made it more viable to develop a port at Laem Chabang, especially in view of the latter's potential for development. It was, therefore proposed that Lerm Chabang be made the site of the country's second commercial port. It was also decided that an industrial port be set up at Mab Ta Phud in Rayong. However, both projects were nearly pulled off the drawing board because of the country's heavy external debt burden. When the external debt service ratio neared the critical level of 30% the Government decided that no more unnecessary and non-urgent foreign loans would be borrowed. The aim of this was to keep external debt borrowings in fiscal 1986 within the US$ 1,000 million ceiling, thus staving off a financial disaster for the country. The Cabinet then decided to set up a three-man committee to review the ESB because it was noted several times that most of the projects required huge foreign borrowings, which could push the external debt service ratio beyond the critical mark. They had 45 days to review the entire programme during which time it was reported that the two deep-sea port projects were the likely victims if the ESB was scaled down in size. lt, therefore, came as a surprise when the Cabinet announced on ChristmaS Eve of 1985 that the entire programme would proceed as planned. According to the ESB plan, construction of the Mab Ta Phud Port will begin in May 1986 and completed by October 1989. Investment in the initial stage would be around 5,820 million baht.. ในขณะเดียวกัน การก่อสร้างท่าเรือน้ำลึกแหลมฉบังจะเริ่มในเดือน 1986 กันยายน ที่ ๕ 1990 กรกฎาคม ลงทุนในเฟสแรกจะรวม 6,860 ล้านบาท ความคิดที่สร้างเป็นท่าเรือใหม่ที่แหลมฉบังได้รับรางวัลสนับสนุนจากของกรุงเทพมหานครและสมาคมตัวแทนยัง (เรา)
การแปล กรุณารอสักครู่..